This RACI (pronounced Ray-See) matrix defines the participation by various roles in completing tasks or deliverables for the project. It clarifies boundaries and ensures that every action item has clear ownership.
Legend:
| HIGHLIGHT | TYPE | DESCRIPTION | ALLOCATION |
|---|---|---|---|
| R | Responsible | Undertaking the actual activity or work. | 1 Team Member per task |
| A | Accountable | Ultimate owner of completion; "the buck stops here." | Exactly 1 Team per task |
| C | Consulted | Two-way communication; provides input or expertise. | No maximum or minimum |
| I | Informed | One-way communication; kept updated on progress. | No maximum or minimum |
BIM Management Rule: While many can be Responsible, only one entity can be Accountable for a single task to avoid confusion and project delays.